ERS Bypass for modification of existing 400kV and 220kV overhead lines for clearance over New Abu Dhabi - Dubai Road (Package A)

Client

Musanada / TRANSCO

Scope performed by Enfras

As part of the Abu Dhabi–Dubai Road E311 (Package A) project, certain existing 400kV and 220kV overhead transmission lines near the Al Samha area require elevation adjustments to ensure the minimum vertical clearance above the proposed roadway. This is addressed through tailored interventions such as inserting new towers, relocating existing ones, or rerouting short sections of the lines based on site-specific conditions.

ENFRAS Scope involves complete ERS, OHL - Project Engineering & project management Support to OHL contractor and render expert supervision by ERS manufacturer's representatives to facilitate above mentioned modifications in two locations, one involving a 400kV DC line (Al Shahama East – Al Dahahma) and the other a 220kV DC line (SHME-SMHG)

Customer/Main Contractor

Ghantoot Tpt. & gen. Const. Est/Centaur Elec Cont LLc

Project Location/ Country

United Arab Emirates